Procurement Handbook 7460.8 Rev 2


11.2 Administering Construction Contracts

F.1  Construction Log. The PHA should maintain a construction log to record potential causes for delays that may be used as the basis for granting time extensions or for denying a request for a time extension.  The construction log should contain daily reports that record at least the following: 

the daily temperature,

the daily amount of precipitation,

delays in obtaining labor and materials, including the duration and the applicable construction trade,

delays experienced by others in completing non-contract public improvements (whether on-site or off-site),

and other causes for delays, such as fires, floods, vandalism, or court orders.