Procurement Handbook 7460.8 Rev 2


11.4 Contract Modifications

A.  General. Occasionally, it is necessary to modify a contract or purchase order to reflect changes in the required effort, period of performance, or price. Contract and purchase order modifications shall be issued in writing in one of the following forms: 

1.   Unilateral modification (a modification that is signed only by the Contracting Officer, such as a change order pursuant to the Changes clause on form HUD-5370, or administrative modification, such as a change in the address of the payment office), or

2.   Bilateral modification (such as a supplemental agreement in which both parties mutually agree on contract changes) that is signed by both the Contracting Officer and the contractor. Bilateral modifications are the preferred method of modifying contracts and purchase orders.

B.   Process. A change order is issued by the Contracting Officer after the award of a contract in any of the contract terms, including specifications, completion time, description of the work, etc., within the scope of the contract.

1.   The Changes clause is included in form HUD-5370 (for construction) and form HUD-5370-C (for non-construction contracts) and form HUD-5370-EZ (for small construction/development contracts).

2.   A change order may be issued unilaterally by the Contracting Officer. In such cases, the contractor is entitled to submit a change order proposal to identify any changes in cost or schedules as a result of the change, and the parties negotiate an equitable adjustment.

3.   Change orders may be issued bilaterally if the contractor agrees to the change in advance. When a change is mutually agreed upon, including price adjustment for concessions made by either party, a contract modification is prepared and signed by both parties to the original contract. See Appendix 15 for a Sample Contract Modification format that may be used for modifications.

4.   Change orders/modifications should include at least the following: a detailed description of the proposed change in work, a reference to the applicable working drawings and specifications, when applicable, a price (credit, debit, or no change) for the change in contract work, estimate of additional time, if any, required to complete the work, the contractor’s itemized breakdown of the cost of materials and labor and an itemized breakdown for any applicable subcontractors, and the change indicate on the architectural or engineering drawings, if applicable.

C.  Limitations on Change Orders. The Changes clause contained in forms HUD-5370, 5370-C, and 5370-EZ, prescribes the specific circumstances in which a change order may be issued. For example, adding the construction of a new building to a modernization contract would not be considered within the scope of the contract or within the authority of the Changes clause but should be considered a new contract (and subject to competition).

D.  Modification Register. The PHA shall maintain accurate records and documentation regarding contract modifications by including a modification register or other record in each contract file. This register is required to provide a permanent record of all actions taken in connection with each contract. The modifications register should generally include information on the following: the number of modifications, a brief description of the change, the cost of the proposed modification, the date submitted to HUD for approval, if applicable, any critical deadline dates, the date of HUD approval or disapproval, if applicable, and the action taken, and the amount of any additional time required by the contractor.