Sealed Bid Procedures

Non-Construction

The following is a flow chart developed by the Buffalo HUD Office to assist Housing Authorities in the development, award and administration of a non-construction contract using the sealed bid  procedures method of procurement. 

 

    Develop an Independent Cost Estimate

    An independent cost estimate of every procurement is 
    required prior to soliciting bids or proposals. 

     Guidance:

    1. Sample Independent Cost Estimate. 
    2. Federal requirements - 24 CFR 85.36.f.1
    3. Procurement Handbook requirements - paragraph 3-15

 
Review Your Procurement Policy
  • Verify your Sealed Bid Threshold. 
  • Review procurement policy for other bidding requirements that may be unique to your Housing Authority.

Instructions to Offerors

Instructions to Offerors - Non-Construction,   form HUD-5369B

Guidance:

  1. The use of  form HUD-5369B  is required for all contracts for non-construction work, reference the Procurement Handbook 7460.8, paragraph 6-3.

Other references include: 

  1. Procurement Handbook Appendix 11
  2. Procurement Handbook Appendix 26, Section C
  3. Mandatory clauses  24 CFR 85.36 (i) 

 

Bidder Certifications

Certifications and Representations of Offerors
Non-Construction Contract, 
  form HUD-5369-C

Guidance:

  1. The use of  form HUD-5369-C   is required for all contracts for non-construction work, reference the Procurement Handbook 7460.8, paragraph 6-3.
Other references include: 
  1. Procurement Handbook Appendix 11
  2. Procurement Handbook Appendix 26, Section D
  3. Mandatory clauses 24 CFR 85.36 (i) 

 

General Conditions

General Contract Conditions, Non-Construction,   form HUD-5370-C

Guidance:

  1. The use of  form HUD-5370-C   is required for all contracts for non-construction work, reference the Procurement Handbook 7460.8, paragraph 6-4.
  2. Required fields within the general conditions need to be filled in by the contracting officer.  Minimum fields that require comments are paragraphs #1a (PHA Name).
Other references include: 
  1. Procurement Handbook Appendix 13
  2. Procurement Handbook Appendix 26, Section C
  3. Mandatory clauses  24 CFR 85.36 (i) 

 

Assembling the bid package.

Develop and insert a table of contents. Sample Table Of Contents

Develop and insert a Bid Form. Sample Bid Form 

Insert Instructions to Bidders for Contract. Guidance

Certifications and Representations of Offerors Non-Construction Contract, 
  form HUD-5369-C.    Guidance

 Non - Collusive Affidavit   Sample Form

Insert General Conditions. Guidance

Develop and insert the Contract Form of Agreement. Sample Agreement

Insert sample partial payment forms.   (optional)

  1. form HUD-51000 - Schedule of Amounts for Contract Payment 
  2. form HUD-51001 -  Periodic Estimate for Partial Payment 
  3. form HUD-51002 -  Schedule of Change Orders 
  4. form HUD-51003 -  Schedule of Materials Stored 
  5. form HUD-51004 -  Summary of Materials Stored 

Insert technical specifications. 


 
Bound Construction Package

It is recommended that the specifications be assembled and bound together into one package. Provide a cover page to identify the construction package.


 

Obtaining Bids
  1. 24 CFR85.36(c)1 requires that all procurement transactions will be conducted in a manner providing full and open competition.
  2. 24 CFR85.36(d)2  requires that bids be both publicly advertised and bids shall be solicited from an adequate number of known suppliers, providing them sufficient time prior to the date set for opening the bids;"
    Guidance:
     
    1. Invitation for Bid - Sample Form 
    2. Advertisement Procedures 
    3. Solicitation Procedures
      • Our office recommends that a minimum of  three (3) sources be contacted to advise them of the pending bid and opening date. 
      • Solicitations may be obtained by phone or in writing. Documentation must be developed to support that bids were solicited from an adequate number of known sources.
      • Bid solicitation log -  Sample Log 
    4. Bid Document Register - Sample Form 

 

Opening the bids
  1. Bids shall be received up until a defined date and time.
  2. Bids shall be opened publicly.
  3. All bids should be recorded in a bid tabulation log to document the status of bids received. 
    Guidance:
     
    • Procurement Handbook Requirements - paragraph 4-13 
    • Bid tabulation log -  Sample Log 

 

Evaluating the bids
  1. All bids shall be reviewed to insure that all required documents are contained within and properly filled out including the "Certifications and Representations of OfferorsNon-Construction Contract, 
      form HUD-5369-C 
  2. The Housing Authority will check to insure that the perspective bidder is responsible, reference 24 CFR 85.36 (b) 8 
  3. Check and document that the contractor's name is not listed on the "List of Parties Excluded from Federal Procurement and Non procurement Programs." listing     documentation 
  4. Verify that the required bid guarantee has been provided.
  5. Check and document that the contractor's name is not listed on HUD's "Limited Denial of Participation" (LDP)    listing, documentation 
    Guidance:
    • Mistakes, Withdraw and Changes In Bid - Procurement Handbook requirements -  paragraph 4-15 
    • List of Parties Excluded from Federal Procurement and Non procurement Programs  - Procurement Handbook paragraph 5-2 .
    • Limited Denial of Participation (LDP) - Procurement Handbook paragraph 5-3.   -   24CFR24.705

 
Determining Cost Reasonableness

A cost or price analysis must be performed in connection with every procurement. 


 
Documenting Rationale for Award
    24CFR(b)9 states "Grantees and sub grantees will maintain records sufficient to detail the significant history of a procurement. These records will include, but are not necessarily limited to the following: rationale for the method of procurement, selection of contract type, contractor selection or rejection, and the basis for the contract price." 

    Guidance:
     

    1. Federal Requirements   24 CFR 85.35 (b) 9 
    2. Determination & Finding for Contract Award -  Sample 
    3. Determination & Finding - Content 

 
H.A. Awards Construction Contract
  1. Award Letter   Sample Letter 
  2. Obtain Performance and Payment Bonds
  3. Notice to Proceed   Sample Letter 
  4. Letter for non successful bids   Sample Letter 

    Guidance:

  1. Procurement Handbook paragraph  4-16D , 4-16F

 
Maintaining Contract Files
  1. Retention of Construction Documents - Minimum of three (3) years after final payments and all other pending matters are closed.  Reference 24CFR85.36(i)11 and the HUD General Conditions paragraph #46 and #47.

 

Contract Administration
     Housing Authorities  will maintain a contract administration system which ensures that contractors perform in accordance with the terms, conditions, and specifications of their contracts or purchase orders. (24CFR85.36(b)2)
    1. Progress Payments  - 
      1. forms 
      2. checklist 
      3. Procurement Handbook 7460.8 paragraph 6-7 C 2.b  

 
Change Orders
    Definition: A change order is a change issued by the Contracting Officer, after the award of a contract, in any of the contract terms, including specifications, completion time, description of work, etc., 
    within the scope of the contract. 

     Sample Forms:

    1. How To Issue a Change Order   Flow Chart 
    2. Change Order Form  Sample Form 
    3. Cost Analysis  Sample Form 
    4. Determination & Finding -   Sample Form 
    5. Change Order Register -  WORD, EXCEL 
    6. Change Order Checklist - Checklist 
       
      Guidance:
    1. Procurement Handbook 7460.8 paragraphs:
      1. Time extensions - 6-7C3
      2. Contract Modifications -  6-10 
      3. Limitations on change orders - 6-10C
    2. Documentation - Determination & Finding

Contract Closeout
         
  1. Final Inspection - procedures
  2. Documentation  - Following final inspection the HA shall notify the contractor to submit the following documentation to the HA:
Contractor's Certificate and Release  Sample Form
Guidance:
  1. Procurement Handbook 7460.8 paragraphs:
    • Completion of work - Documentation -  6-7C6d

 

Warranties
    The Housing Authority is responsible for performing warranty inspections and promptly notifying the contractor in writing to remedy any defects. 
    (Procurement Handbook 7460.8, paragraph 6-7 C 5)

    Warranty Inspection Form   Sample Form